Case Study
Replacing a wet scrubber by a dry injection finishing process
Replacing a wet scrubber by a dry injection ? nishing process The challenge The customer, a Belgian Energy from Waste plant, decided to modernise its site with the key objective of reducing acid gas emissions to half the regulatory levels (i.e. 5mg HCl/Nm 3 and 25mg SO 2 /Nm 3 ). Furnace no 4, capacity 16t waste/h, currently uses a semi-wet acid gas removal unit where fl ue gases are treated with milk of lime to neutralise acid gas