Remove Paint, Corrosion and Profiling Structural Steel Bases in Amusement Park Play Facility
©2008 Sponge-Jet Inc. All rights reserved. 1 Remove Paint, Corrosion and Profiling Structural Steel Bases in Amusement Park Play Facility Overview: • Structural steel bases in park’s play facility were corroding in dark, humid setting • Coating failure in many areas • Park operates 9am to 10pm, year-round • Short window of opportunity for blasting and painting; allowed only during non-operating hours Objective: • Remove paint, existing corrosion where necessary and profile the superstructure’s steel bases, then re-coat Project 856 ©2008 Sponge-Jet Inc. All rights reserved. 2 Remove Paint, Corrosion and Profiling Structural Steel Bases in Amusement Park Play Facility Substrate: steel Surface Condition: peeling paint; mid-grade rust on frame bases Specified: •