Case Study
REF 542plus Maintenance Exchange Unit service Statoil offshore platform, Kvitebjorn, Norway
— SERVICE / SUCCESS STORY REF 542plus Maintenance Exchange Unit service Statoil offshore platform, Kvitebjorn, Norway Time-efficient and easy relay upgrade and replacement with ABB’s Maintenance Exchange Unit service. Project at a glance Customer: Statoil Segment: Oil and gas ABB service: REF 542plus Maintenance Exchange Unit Customer challenge The customer had an existing installed base of an older version of ABB’s REF 542plus protection relays on their platform. The customer identified the need to replace these relays to avoid unscheduled operation downtime due to aging equipment. To optimize their operations, the customer had also identified a need for additional relay functions, as well as the necessity to increase maintenance scheduling predictability. Another cha