RAS pumps were clogging on average 21 times per week.

RAS pumps were clogging on average 21 times per week.

? RAS pumps were clogging on average 21 times per week. ? Lots of time was spent clearing clogs, rather than doing important maintenance. ? Manpower, overtime and equipment was costing $3,000 per week ? Three DERAGGER TM s installed Fall 2017, with Real Time Pump Protection TM used to detect rags and run clean cycle. CLOG REDUCTION: Average 21 times per week, down to Zero. Deragger Inc. 1220 Main St, Suite 400, Vancouver, Washington, 98660 (360) 215-7676 info@deragger.com www.deragger.com ? Complete reduction in ragging. ? Big saving in manpower, overtime and equipment —estimated by the City at roughly $100,000 in first eight months. ? Press coverage in newspapers and television: see www.deragger.com/palestine. Energy and cost saving calculations are as reported b