Case Study
Railway Sleeper Factory, Doncaster
KKB GROUP INNOVATIVE REGENERATION SERVICES Remediation Recycling Plant Hire Plant Sales Demolition Civil Engineering In May 2013 KKB Remediation Limited were commissioned by Trackwork Moll, a manufacturer of high quality pre-stressed concrete railway sleepers, to construct a railway siding at its new factory in Doncaster. The site covered an area of 50,000 square metres and had 10,000 cubic metres of soil stockpiled on it from the main construction works.1500 metres of railway track and sleepers were lifted by KKB ready to be reused on site. Our contract was to construct the railway bed for the rail crane and siding and to construct it using materials from the site which meant the excavation, screening, processing and relaying of 20000 square metres of railway ballast. The ra