Providing Welfare And Site Supervision
get in touch 01899 309 100 www.greencatrenewables.co.uk CASe STudy – arKhill wind f arm KEY DATA ? No. Turbines: 8 ? Turbine Type: Enercon E-48 (800kW) ? Local Authority: Angus Council ? T urbine Installation Start: 10 December 2012 ? T urbine Installation Finished: 15 February 2013 ? Commissioning Complete: 29 March 2013 ? Production: 18,500 MWh annually Client: enerCon Gmbh Green Cat renewab