Case Study
Project Specific Partnering Contract Flood Alleviation Scheme At River Lavant, Chichester
PROJECT SPECIFIC PARTNERING CONTRACT FLOOD ALLEVIATION SCHEME AT RIVER LAVANT, CHICHESTER Very high profile 'Project Specific Partnering' Contract under ECC Option 'A' Form of Contract. Works include the construction of 2No. twin 1200mm ID Mechanised Pipejack tunnelled road crossings of 190m & 150m in length (680m total), including the busy A27(T) trunk road to link diverted flood waters to nearby lakes. Ground conditions being very dense sa