Project Overview – Cooper House Farm Olney Office Park, 1 Osier Way, Olney, Buckinghamshire, MK46 5FP Tel: 01234 482482 Email: sales@g2energy.co.uk Web: www.g2energy.co.uk “Connecting you to the grid” PROJECT STATISTICS... Project: Cooper House Farm Location: Lancashire DNO: Electricity North West (ENW) Voltage: 6.6kV g2 Energy Works Awarded: Contestable, Client-side Completed: March 2016 SCOPE OF WORKS – CONTESTABLE g2 Energy were responsible for the Civil & Electrical Design & Build for the Contestable Works which included the Supply & Installation of: ? 6.6kV ring main unit and protection relays in a “loop in loop out” configuration ? Battery and charger, plus all multicore cabling ? ENW approved 6.6kV cabling from the Point of Connection to the Substation, incl