Pointe Du Bois, MB - East Forebay Wall

Pointe Du Bois, MB - East Forebay Wall

Y ear: Technology: 2002 - 2003 Rock Anchors Over a 13-month period spanning most of 2002 and into 2003, Geo- Foundations completed its second large anchoring project at the 90-year- old Pointe du Bois Generating Station. This $3.5M project involved anchoring the East Forebay Wall and Spillway Bays 121 through 133. Gaining access to this complicated and restricted job site was one of the many challenges to completing this project. Work began