Case Study
PETRONAS Tower 3: Cementaid contributed its Hydrophobic Pore-blocking (HPI) integral waterproofing system
PETRONAS Tower 3: Cementaid contributed its Hydrophobic Pore-blocking (HPI) integral waterproofing system
Project Page: PETRONAS Tower 3 (Lot C @ KLCC) PETRONAS Tower 3 (Lot C @ KLCC) Petronas Tower 3 is another addition to the world class Petronas Twin Towers offices. The 58 storey Petronas Tower 3 featured a 6 level extension to the Suria KLCC shopping mall with the remaining floors are the offices. For this prestigious project, Cementaid contributed its Hydrophobic Pore-blocking (HPI) integral waterproofing system in the form of 3CC System for the 3 level water tank which is situated at the basement. The HPI treated concrete becomes hydrophobic and permanently waterproofed and ensuring leakage (if any) is localized, easily identified and repaired speedily, even when the structure is still under ponding test during construction period, prior to handover. Cementaid’s HPI concrete with more