PEMBROKE (UK) Combined Cycle Gas Turbine -5x400 MW

PEMBROKE (UK) Combined Cycle Gas Turbine -5x400 MW

Pages 1 Pages

CASE STUDY Stanton Bonna Concrete Limited ? Littlewell Lane ? Stanton-by-Dale ? Ilkeston ? Derbyshire ? DE7 4QW Tel: 0115 9441448 ? info@stanton-bonna.co.uk ? www.stanton-bonna.co.uk CASE STUDY PEMBROKE (UK) Combined Cycle Gas Turbine - 5x400 MW THE PROJECT Client Project Management Power Date of supply 2010 Value 2,46 M€ Details Design and supply of Pressure Pipes and special pieces for the cooling water pipework at the Combined Cycle Gas Turbine 2000 MW power station in Pembroke (UK). Characteristics The discharge pipes connect the condenser to the discharge point. Type of pipework : RCCP Reinforced Concrete Cylinder Pipe DN : 2000mm Total Length : 1600 m Type of assembly : The pipes are assembled by welding (SL). Performance: PS (Working Pressure) = 1.8 bars PMF (Maximum Opera