Case Study
Paper Mill
GE Energy Results Reduced downtime from failed cell stack modules • Previous annual downtime approximately 315 hours • Previous downtime cost approximately $240k/yr Avoided $1.9MM in new equipment costs • Eliminated cost of buying new drives ($1.5MM) • Eliminated cost of buying new cell stacks ($400K) Extended life cycle of 30+ drives for customer • Completed refurbishment of all drives in time to meet critical shutdown schedule “Not only has the