Case Study
Our client’s desire to clean up a former manufactured gas plant came with its share of challenges
Project highlights Client challenge Our client’s desire to clean up a former manufactured gas plant came with its share of challenges—literally from all sides. The site was nestled next to a recreational bike path and had a 6,000-gallon per minute creek running through an underground culvert beneath it. Removing the coal tar impacted soil and demolishing the old plant infrastructure while not disturbing the community’s use of the path was further complicated by having to divert the underground culvert during construction. With a goal of having this project on their books by the end of the year, our client turned to its longstanding partner, Haley & Aldrich, to deliver a holistic design/build approach on time and on budget. Our approach With just three months to complete the project, Haley