Case Study

OSOGBO SOLAR POWER PLANT

OSOGBO SOLAR POWER PLANT

Pages 2 Pages

OSOGBO SOLAR POWER PLANT Osun State, Nigeria, West Africa Ownership: Osun State Signature of contract agreement: October 2015 Contract implementation: May 2016 Total power installed: 13 MWp, grid connected Commissioning: October 2018 Operations: Local investors Maintenance: Vergnet and local partners Contract agreement signature ceremony Osun State house / Abuja Solar PV Solutions Deliver Energy and Cost Savings for Osun State, Nigeria The Osogbo solar power plant will be the first of its kind the West African sub-region. It is based on an innovative public/private partnership between France and Nigeria, initiated by both Presidents in 2014. The project integrates the Engineering, Procurement and Construction (EPC) of a 13 MWp solar PV plant, the first of such magnitud