Case Study
Offshore Gabon, Central Africa
LDD, an Acteon company, put their design capabilities to the test in a jacket installation project in the Ebouri Field, offshore Gabon. The job was to drill and grout 4 no. through-leg 42" tubular piles in 81m of water. Working directly on the project’s critical path, on a vessel with a very high day rate, LDD’s performance and contingency measures had to be first class. The sub-base consisted of hard mudstone and sandstone so they went prepared