Case Study
OEM modifications reduces unplanned downtime and maintenance costs
OEM modifications reduces unplanned downtime and maintenance costs - DRB Group DRB HELPS WASTE-TO-ENERGY GIANT REDUCE UNPLANNED DOWN TIME WITH OEM MODIFICATIONS. CHALLENGE The customer uses the grabs to mix the waste and feed it into the Boilers. The nature of this process puts a lot of stress onto the grab arms, leading to premature wear and failure. Therefore any unplanned downtime has an effect on production. SOLUTION DRB modified the OEM grab arm, creating a new design that maintained their functionality, strength, and durability even after reducing their profile and weight. VALUE DELIVERED DRB’s technical intelligence and practical experience reduced the customer’s risk by providing a solution that increased reliability and minimised potential downtime, which could equate to tens of t