Case Study
NWEP Phase 3 Civils
“Project completion works on lineside and depot civils” NWEP Phase 3 Civils NWEP Phase 3 Civils New sidings perimeter fence T he initial scope included the installation of driver walkways and lighting column foundations at Blackpool De- pot Sidings. The driver walkways were con- structed to incorporate sleeves, chambers and ducting to fa- cilitate the installation of 20nr lighting columns. All secondary ducting routes were connect- ed back to the primary route to enable cable installation from the distribution point straight to the light. GRP handrails were installed where required. Following successful completion of the initial works Pod-Trak were awarded further works along the entire NWEP Phase 3 route be- tween Preston and Blackpool. At various locations along the rou