CASE STUDY NPOWER, LEEDS HEADLINES KEY FACTS Project title: Location: Seacroft, Leeds Services: Mechanical & Electrical Client: Npower Contactor: Caddick Construction Scheme Value: £1.15 million Duration: 32 weeks G&H divisions: Building Services an additional AV contract after impressing throughout the scheme engineers on-site 2,815 SQM 30+ WORKED WON of exposed M&E services installed CASE STUDY HOW WE DID IT This was one of the most aesthetically impressive schemes we have delivered due to the large array of services on display. Divided in two sections, our work design and build the entire mechanical and electrical services. spaces, meeting rooms, kitchens, breakout areas and washrooms. The exposed nature means heat recovery units, ductwork and electric