Case Study
Nice - Pak, Westwood Park, Wigan
Nice-Pak, Westwood Park, Wigan Green Remediation Ltd Case Study 10317 Nice Pak, Westwood Park, Wigan www.greenremediation.co.uk Green Remediation Ltd, HQ Building, 2 Atherton Street, Manchester, M3 3GS www.greenremediation.co.uk Tel: 0161 775 5393 1 Case Study – 10317 – Westwood Park, Wigan Project Overview Green Remediation Ltd were employed to carry out the demolition of the existing former Santander building, followed by an earthworks and stabilization package. To be constructed on this site was a 38,000 m2 warehouse and 41,000 m2 of access roads, yards and car parking. Client: Vinci Construction UK Date: May to November 2015 Duration: 30 Weeks Location: Westwood Park, Wigan Contents Project Overview & Contents 1 Service