Case Study

Nestlé Anderson, Indiana

Nestlé Anderson, Indiana

Process • Phase 1: Dematic was contracted to conduct an analysis that yielded a design concept and favorable ROI vs. a conventional alternative. • Phase 2: A detailed solution design and simulation was performed. • Phases 3 & 4: The system was engineered and implemented on time and on budget. • Phase 5: Today, Dematic provides a variety of aftermarket services to protect the investment. System Overview Four manufacturing lines produce up to 160 pallets per hour, conveyed directly to an Automated Storage/ Retrieval System (ASRS). Two separate temperature zones within the ASRS allow for eventual migration to aseptic packaging (where less expensive, non refrigerated storage may be utilized). The 8-aisle, triple deep storage system provides a high level of redundancy and se