the River Restoration Centre Case Study Series This site was last visited by RRC staff on 20 th September 2010 Tel/fax: 01234 752979 Email: rrc@therrc.co.uk http://www.therrc.co.uk Montford Weir Removal, River Calder Improvement Project Weir removal, habitat enhancement, bank stabilisation, woodland planting Tributary and Main River: Pendle Water, River Calder County: Lancashire Project start date: June 2010 Project end date: October 2010 Length: 500m Cost: Unknown Grid reference: SD840369 Site background and objectives The River Calder Improvement Project is an ambitious project led by the Ribble Rivers Trust. While there are existing stretches of natural gravels and riverin