Mohican-Battenkill Article VII Project

Mohican-Battenkill Article VII Project

Pages 1 Pages

Mohican-Battenkill Article VII Project Transmission Construction | Moreau, NY Scope of Work This project consisted of reconstructing and reconductoring approximately 14.2 miles of two existing 115kV electric transmission lines in Saratoga and Washington Counties. The two lines are the Mohican-Battenkill Line 15 and a portion of the Mohican-Luther Forest Line 3, formerly known as Mohican-North Troy Line 3. The Project originated at the Mohican Substation in Moreau, NY, and ends at the Battenkill Substation in Easton, NY . Services Employed 131 new steel structures 134 drilled pier foundations 5 vibratory caisson foundations 4 H-pile foundations 35,000’ of gravel roads 40,000’ of matted roads 28 circuit miles of conductor and shield wire replacement