MET SQUARE HIGH RISE

MET SQUARE HIGH RISE

Pages 1 Pages

Key Achievements Application Technique Market sector Owner Main contractor Engineer Keller business unit (s) MET SQUARE HIGH RISE MIAMI, FLORIDA • The original pile installation schedule was cut from 14 weeks to 8 weeks, saving time in the client’s schedule. • The project was completed without disturbing ancient Tequesta Indian remains. • The project Met Square is a 43-story multi-use high rise with a 7-story podium to be completed in 2018. The structure will have an 18-screen Silverspot cinema, restaurants, and a 391-unit apartment tower all being built over a Tequesta Indian Settlement. Soil conditions consisted of limestone with varying degrees of cementation typical of the downtown Miami area. • The challenge Located in downtown Miami, the densely populated area is swarmed with ve