Case Study
Mayflower Cruise Terminal
CASE STUDY CLIENT ABP (Associated British Ports) LOCATION Southampton VALUE £5.08M DATE October 2014 April 2015 About the project. We were delighted to have worked with ABP to refurbish the Mayflower Terminal in Southampton. The works involved: • Refurbishment of the external drop-off point and car parking • Replacement of the external northern façade • The remodelling of internal layouts • The addition of an internal lift and two-storey extension of the terminal into the adjoining existing grain store building together with new metal doors and screens As well as the above, existing mechanical and electrical systems were renewed as part of the alternations, including new toilet facilities, provision of a new VRF heating / cooling system and replacement of the e