Case Study
Maurid Marul Main Production Station (MMPS)
Project P4: Maurid Marul Main Production Station (MMPS) cASe StUDY LocAtion Oman enD USer Petroleum Development Oman (PDO) contrActor Electrowatt Engineering conSULtAnt Dynaflow International Inc., U.A.E. PiPe SYSteMS UtiLitY Flowline coMPLetion DAte 2001 DeScriPtion 29 KM, High Pressure Pipeline PiPe SYSteM The project called for the production of a Glass Reinforced Epoxy Pipeline, 250mm in diameter designed for a pressure of 50 Bar, and temperature of 500C, over 29 km of desert terrain traversing roads and wadis. The pipeline was designed in accordance with internationally accredited and approved manufacturing and logistics procedures. GRE qualification testing was done as per Shell DEP 31.40.10.19 Gen. ScoPe Our scope entailed a single point responsibility, whereby we assume ful