Mary Street Lift Station Replacement, City of Redding, Redding CA
Mary Street Lift Station Replacement, City of Redding, Redding CA Water Works Engineers designed the replacement of the City of Redding’s Mary Street Lift Station. The existing 40-plus year old lift station was near the end of its useful life, and was replaced and expanded to a peak ?ow of 2600 gpm to meet the growth in its service area. The pump station is near the Sacramento River Trail and high-end homes, so system reliability, aesthetics, security, and odor control were key design factors for the new pumping facility. The new lift station uses parallel sets of dry-pit submersible pumps in a dual wet-well arrangement for system reliability and redundancy. A wall-mounted, inline raw sewage grinder grinds in?uent solids and minimize the potential for the pumps to “rag up” . Smaller pumps