Case Study | VLT® AutomationDrive FC 302 Total stop to local pollution from diesel exhaust Maersk Supply Service – shore power supply with a payback period of less than 5 months Due to the low oil price and challenges in the oil and gas industry, Maersk Supply Service has since 2016 had some of it’s anchor handling vessels and platform supply vessels in layup waiting for the next job. Up to 10 vessels have been parked between jobs in the Port of Fredericia, Denmark, where the location and facilities are well-suited for longer-term storage. drives.danfoss.com2 Danfoss Drives · DKDD.PC.948.A1.02 Warm storage costs To avoid any damage to vital systems due the effects of a long-term standstill period, the ships are stored “warm” – which means that the diesel engines are preheated an