Case Study

M8, M73, M74 Glasgow Motorway Improvements

M8, M73, M74 Glasgow Motorway Improvements

M8, M73, M74 Glasgow Motorway Improvements 4,050m2 Stratec W400/50PET High Strength Woven Geotextile Main Contractor: Ferrovial Lagan JV . April 2015 Case StudyThe Problem Ferrovial Lagan was faced with many challenges on this 500m infrastructure project. However just one of the particular challenges it faced was the requirement to traverse extremely weak ground and provide a

Join for free to read