Case Study

Lincoln Bypass

Lincoln Bypass

Trusted to deliver Case study // Lincoln Bypass CLIENT CONTRACT VALUE DATE COMPLETE BAM Nuttall £180k October 2017 THE CHALLENGE The A15 Lincoln Eastern Bypass is a 7.5km road designed to improve Lincoln’s infrastructure, encourage growth, minimise traffic congestion and enhance the inter-city environment. Lincolnshire County Council, the Department for Transport (DfT) and the three district authorities, City of Lincoln Council, West Lindsey Council and North Kesteven District Council required us to remove track in order to introduce a new bridge as part of the bypass scheme. WHAT WE DID Stobart Rail removed 90m of track to allow sufficient room for ballast ramps (15m) and working space for the hydraulic skidding system to push the bridge into its final position, where it will sup