Lift IQ Service Reduces Time to Restart 42 Wells to 2.8 Hours—4 Minutes per Well, Ecuador

Lift IQ Service Reduces Time to Restart 42 Wells to 2.8 Hours—4 Minutes per Well, Ecuador

Pages 1 Pages

CHALLENGE Reduce time needed to restart wells and avoid deferred production after unexpected power supply interruptions. SOLUTION Use Lift IQ* production life cycle management service and support from Artificial Lift Surveillance Center (ALSC) to monitor operations prior to the interruption, remotely restart the wells, and confirm the wells had successfully restarted after the interruption. RESULTS ¦ Reduced time to restart wells from 16.8 hours to a record 2.8 hours—an average of 4 minutes per well. ¦ Reduced deferred production by 72%, representing savings of USD 190,000. Unscheduled power supply interruption causes difficulties in restarting wells A power supply interruption for a customer in Ecuador represents a major issue for production and logistics. Although these