Case Study
Liability Project (NCRP)
North Central Reliability Project (NCRP) 138kV TO 230kV Conversion Project New Jersey Installation of foundations for the conversion of an existing 138kV transmission line to a 230kV transmission line between the West Orange Substation, Roseland Switching Station and the Metuchen Switching Station. Scope of Work: Our scope of work revolved around installing 186 foundations consisting of 156 drilled shafts ranging in diameter from 7