Leyton Sixth Form College

Leyton Sixth Form College

? CASE STUDY - LOUVRES Project Leyton Sixth Form College Location Leyton, London E10 Products W35SZ 75mm blade site assembly clip-in louvre screens Finish Polyester powder coated 40 microns to RAL7000 Squirrel Grey Job Type Supply and installation Programme 4 weeks manufacturing and 7 days installation Completed September 2010 Architect Archial Architects Main Contractor Wates Construction Sub-Contractor MARS (Construction) Description EDS were a