Case Study
Late discovery of cultural resource artifacts poses no problem to construction schedule > Haley Aldrich
Late discovery of cultural resource artifacts poses no problem to construction schedule > Haley Aldrich
Late discovery of cultural resource artifacts poses no problem to construction schedule > Haley Aldrich Providing clear direction on an uncertain road A clean energy initiative takes shape Moxie Energy is an independent energy producer that has developed power plants in central Pennsylvania to take advantage of the abundant natural gas resources of the Marcellus Shale Region. Natural gas has a significantly cleaner energy profile than other fossil fuels, and gas-fired combined-cycle power plants are needed to replace aging power generation in several areas of the country, including the northeast. The company originally chose to locate this plant adjacent to the transmission grid, providing a nearby interconnect. But as project closing neared, the regional grid operator informed Moxie that