Case Study
Lady Loretta
PROJECT FACT SHEET LADY LORETTA SCOPE • A greenfields infrastructure project ranging from portal establishment to point of readiness for mine production KEY PROJECT OUTCOMES • Project delivered 2 months ahead of schedule at below budget project costs for client • Average 252m/mth development advance achieved versus 214m/mth scheduled • Second jumbo scheduled for mid-p