Case Study
Laúca HP Plant
HYDROELECTRIC POWER PLANTS LAÚCA HP PLANT LOCATION ? Malanje (Angola) CUSTOMER ? GAMEK (Ministry for Energy and Water PROJECT SCOPE: Electro-mechanical assembly work on the 2,070 MW Laúca hydroelectric power plant AMOUNT ? EUR 151 million START DATE ? November 2015 END DATE ? August 2018 CHARACTERISTICS: ? General data ? Power capacity: 6 x 334 MW + 1 x 67 MW ? Main plant with six 334 MW turbine-generators and mechanical and electrical BOP ? A 67 MW ecological flow turbine and mechanical and electrical BOP ? Hydromechanics ? Lifting systems ? Penstocks and sluiceway gates ? 400 kV and 200 kV substation ? 15 kV , 400 kV and 220 kV lines between the substations and the plantsMalanje (Angola) ANGOLA AFRICA HYDROELECTRIC POWER PLANTS LAÚCA HP PLANT