Laboratory & Office Fit-out
www.bbi-uk.com www.pje-uk.com Group PROJECT: Laboratory & Office Fit-out Location: Glaslyn, Newport Value: £3.8M Timescale: 16 weeks The client Dwr Cymru Welsh Water is the sixth largest regulated water company in England and Wales, serving around 1.2 million households and more than 110,000 business customers. The brief To convert a former office space into a new laboratory with office facilities for Welsh Water’s water testing services in just 16 weeks Project delivery We had our work cut out for Welsh Water with this task as the project, which would normally take in the region of six months, had to be completed in just 16 weeks. Our challenge was to create a building that served two purposes – three quarters was given over to technical laboratories for water testing, with the