Johnson & Johnson
Following a competitive tender Clifford Devlin was appointed to deliver a design and build contract to refurbish Block B of Johnson & Johnson's Head- quarters in High Wycombe which comprised a fitness suite, restaurant, meeting area and coffee bar. To minimise disruption and disturbance to the staff at the facility, which remained open and fully operational throughout, most of the works were undertaken out-of-hours and conducted between 6pm and 2am. A very high quality specification for the project required us to employ the services of two specialist design agencies, Vecs and TMV, to help facilitate and implement the plans and vision created by the client's architect. While the works were segregated into three mini- projects, to minimise programme the works to all of the floors were carrie