Integrated solution of GaugePro Echo digital reamer and AutoTrak G3 RSS cut plan by 6 days

Integrated solution of GaugePro Echo digital reamer and AutoTrak G3 RSS cut plan by 6 days

Pages 2 Pages

Integrated solution of GaugePro Echo digital reamer and AutoTrak G3 RSS cut plan by 6 days Challenges • Drill and clean entire section, including pilot hole, in one run • Minimize NPT and damage to downhole tools • Build inclination from 29° to 47° at BUR of 2.5°/100 ft (30.5 m) • Set casing between a sand zone and a slump zone Results • Under reamed 124 ft (38 m) of pilot hole in one hour and eliminated a dedicated reaming trip, saving 30 hours of expected rig time • Achieved minimum BUR of 2.5°/100 ft (30.5 m) • Recorded no downtime or tool failures, reducing 12-day AFE plan by 50% A deepwater operator in the Gulf of Mexico planned a well with 2.5° build-up rate (BUR) to reach geological targets and avoid nearby wells. In the build section of the well, the operator also