Installation: Global Tech I www.windcarrier.com Bold Tern loaded with towers and nacelles copyright: Global Tech I / Henthorn The Project Fred. Olsen Windcarrier’s specialist jack-up vessels the Bold Tern and the Bold Tern in partnership with Global Wind Service (GWS) installed turbines at the Global Tech I wind farm in the German North Sea. The full scope of work was to transport and install a total of 75 towers and nacelles and 22 rotor stars in eight months. Fred. Olsen Windcarrier and GWS started on the project in January 2014 and completed the  nal turbine in late August 2014. Global Tech I was the third project in German waters for Fred. Olsen Windcarrier since the launch of the Brave Tern and her sister ship Bold Tern in 2012/13. Global Tech I will occupy an area of r