Hydratight Mechanical Connectors facilitate industry first hot-work free platform shutdown

Hydratight Mechanical Connectors facilitate industry first hot-work free platform shutdown

Pages 2 Pages

Case Study The Challenge A Shell/ Esso operated sole pit clipper platform in the southern North Sea required twenty six pipework tie ins. The work had to be completed within a tight 10 day shutdown to minimise loss of production. The Solution Hydratight and AMEC Process and Energy Limited were engaged to undertake an industry first hot-work-free platform shutdown using Hydratight Morgrip ™ Mechanical Connectors. Hydratight’s Morgrip ™ Conne