Case Study
Hybrid Power System - Repeater Site in Amarillo, TX
Hybrid Power System Repeater Site in Amarillo, TX This is the site of a cellular repeater along a remote stretch of highway near Amarillo, TX. At the time of installation there was no utility connection at this cellular repeater site, so Alpha designed a reliable Hybrid Power System (HPS) with dual generators. The large energy requirement of this site, about 24kWh per day, and a fixed budget meant that the system had to be highly dependent on generator power for increased reliability. To provide the most efficient solution possible, Alpha installed alternating dual generators to reduce maintenance visits to about once per month and significantly reduce fuel consumption. The HPS24-1050/1500-2GEN is extremely reliable due to its alternating generator topology. The system is size