Case History H7188 Cooling tower Nebraska 10” Green Thread ® Pipe and Fittings The original system, installed in 1992, was a single tower using 24” PVC. Three years later new isolation valves were installed and were incorrectly wired. When the pumps were started, the valves closed dead heading the line. The chiller plant was redesigned, switching to three chillers and using 10” steel piping that has failed due to internal and external corr