Case Study
Horizon View No. 3 BPS Rehabilitation
Horizon View No. 3 BPS Rehabilitation Project Description RH2 evaluated the City of Bellevue’s Horizon View No. 3 Water Pump Station to stabilize pressures to a closed zone within the Summit neighborhood by evaluating the existing conditions, performing a hydraulic and pump station capacity analysis, and recommending mechanical and electrical improvements, and a standby generator for the pump station. Customers were experiencing pressure fluctuations of 20 psi because the pump station was controlled by a hydropneumatic tank. A combination of economic, social, and environmental issues were considered as part of a triple bottom line analysis to evaluate various pumping alternatives and generator systems. Preliminary Design Our team performed a detailed hydraulic analysis as part of the preli