Case Study

Hinksey Stream bypass channel

Hinksey Stream bypass channel

the River Restoration Centre Case Study Series This site was last visited by RRC staff on 22 nd August 2013 Tel/fax: 01234 752979 Email: rrc@therrc.co.uk http://www.therrc.co.uk Tributary and Main River: Hinksey Stream, River Thames County: Oxfordshire Project start date: 2011. Main construction between September & October 2012 Project end date: Summer 2013, after planting-up and addition of river habitat features (wood and rock) Length: 100m Cost: £ 80,000 (approx.) Grid reference: SP521045 (Upstream) Design and Implementation Design works started in 2011. It was initially thought that the project could be carried ou