Case Study

Genesis Energy

Genesis Energy

RHOADS SOLUTION The work that needed to be completed included multiple piping jobs, steel repair and installing pipe hangers, in addition to blasting and painting. To satisfy all of these needs, Rhoads dry-docked both vessels, a 400-foot barge and 137-foot tug, end-to-end in our facility. We expanded our skilled labor crew to a team of more than 65 and went to work on an around-the-clock schedule, given the contract’s 34-day completion