Case Study

Gallows Hill

Gallows Hill

get in touch 01899 309 100 www.greencatrenewables.co.uk caSE Study – gallowS hill KEY DATA ? No. Turbines: 1 ? Turbine type: Enercon E48 (500kW) ? Date Work Commenced: February 2006 ? Date of First Generation: November 2012 ? Annual Electricity production: 1,500MWh tEchnical Support and projEct managEmEnt green cat renewables provided t echnical support and project management during planning conditi

Join for free to read