Fuel Gas Train Survey Improves Plant Safety

Fuel Gas Train Survey Improves Plant Safety

Pages 2 Pages

INDUSTRIAL Fuel gas train surveys help customers improve plant safety, minimize downtime, enhance equipment performance and increase staff productivity. Fired Heaters Fuel Gas Train Survey Improves Plant Safety RESULTS • Plant avoided shutdown costs of $100K/day • Overpressure protection solutions improved plant safety • Thermal Oxidizer solution resulted in $20K savings APPLICATION Fired Heater Fuel Gas Train CUSTOMER Corn Milling Plant in North America CHALLENGE The plant is an old facility that has been expanded over time and had several pressure control challenges. The plant expansion project changed the process conditions and impacted regulator sizing and overpressure protection systems. However, the plant staff lacked the skills required to detect the undersized regulators