The challenge A very large and highly serviced project with an extremely high environmental performance criteria including reliability and redundancy which have to been demonstrated and recorded for building operation certification. Crown House Technologies was required to to design a commissioning and performance testing strategy that delivers fully tested & integrated MEP systems, working with the building fabric to provide the correct environment conditions in a reliable and safe manner. Our approach We started by reviewing the design and holding a series of commissioning workshops with all of the interested parties (client users, project managers, the validation team and MEP Consultants). The planning of the testing and commissioning and the final system and building performance tests