Floor Seal PowerPump System Cuts Six Weeks from Webcor’s Construction Schedule at San Francisco General Hospital
Floor Seal PowerPump System Cuts Six Weeks from Webcor’s Construction Schedule at San Francisco General Hospital
Floor Seal Technology technicians use PowerPump to apply the concrete moisture emission control and substrate leveling system. www.floorseal.com | 800.572.2344 Floor Seal PowerPump System Cuts Six Weeks from Webcor’s Construction Schedule at San Francisco General Hospital FLO R O L SEA T E C H N O L O G Y For the residents of San Francisco and Northern San Mateo County, completion of the 284 bed San Francisco General Hospital Replacement cannot arrive soon enough. Once opened in 2015, the new hospital will serve as San Francisco’s only Level 1 Trauma Center. Webcor Builders, the prime contractor for the project, sought innovative approaches to expedite the construction schedule. The company selected Floor Seal Technology’s PowerPump System for the application of the co