Case Study
Flood Risk For A North Wales Primary School Development
Key Statistics Technical Full 1D/2D Hydraulic Modelling, Hydrology Assessment & Flood Consequence Assessment Money Planning required to facilitate a multi-million- pound education investment Risk Ensure that the new site would be flood free and provide betterment to the nearby Glasdir Estate, which had previously suffered from flooding. People Part of a large project team led by Denbighshire County Council Time 12-month Waterco project over 4 stages Value Provided the client with additional advice on Infiltration testing techniques to inform drainage strategy Compliance In accordance with Technical Advice Note (TAN) 15 and approved by Natural Resources Wales (NRW) Environment The scheme promoted amenity space and landscaped features that incorporate drainage 01824